One asset.
Two pathways.
A data center is a physical asset embedded in an institutional setting. Trace how sites in the US and China secure land, power, capital and permission.
New evidence · 19 October 2026
Newly added to the research atlas. Source publication dates and evidence status appear in each record.
Follow how infrastructure takes shape.
1. United States
1.1 Full grid
AWS / Talen Susquehanna Data Campus
Interconnection classification, reliability studies, and cost allocation for large co-located load
Internal source tag US02
- Location
- Pennsylvania
- Grid / utility
- PJM / PPL Electric transmission zone
- Status at corpus cutoff
- RESTRUCTURED; OPERATIONAL
- Power model
- Revised nuclear PPA plus public-grid delivery; April 2026 front-of-meter transition confirmed in Q2-2026 filing. Up to 1,920 MW is the contractual future maximum, not current campus load.
- Power evidence
- Susquehanna nuclear output under long-term PPA; electricity physically remains within PJM arrangements
- Legal dependency
- FERC Order 189 FERC ¶61,078; PJM interconnection service agreement
- Contract dependency
- Long-term offtake reduces merchant exposure; termination protection not established
- Capacity boundary
- Maximum power under revised PPA through 2042; not current delivered campus load
- Uncertainty
- Filed disclosure confirms April 2026 transition, but current delivered campus load is not established. PPA can serve more than the adjacent campus.
Microsoft / Constellation Crane Clean Energy Center
NRC approvals, restoration schedule, environmental permits, and delivery before contracted date
Internal source tag US04
- Location
- Pennsylvania
- Grid / utility
- PJM
- Status at corpus cutoff
- PERMITTING; UNDER_CONSTRUCTION
- Power model
- Long-term grid-delivered nuclear PPA supporting restart; physical and legal delivery terms only partly public.
- Power evidence
- Grid-delivered nuclear PPA. Microsoft purchases energy to match PJM data-center use; no dedicated wire, specified receiving campus, or financial-only contract character is established.
- Legal dependency
- NRC restart reviews and Pennsylvania DEP permits
- Contract dependency
- PPA supports restart revenue; delay/termination remedies not public
- Capacity boundary
- Approximate plant output after successful restart; not current delivered capacity
- Uncertainty
- Regulatory status controls over promotional timing. Draft environmental findings and state certification are not permission to operate; remaining restart and NPDES actions are unresolved.
Switch Citadel Campus (Tahoe Reno)
Converting projected 2 GW campus scale into staged, contracted, grid-served capacity
Internal source tag US05
- Location
- Nevada
- Grid / utility
- NV Energy / WECC
- Status at corpus cutoff
- OPERATIONAL
- Power model
- Utility supply plus power-purchase/renewable attribute arrangements
- Power evidence
- NV Energy supply and long-term renewable power arrangements; Switch claims 100% renewable operations
- Legal dependency
- Utility tariffs, land development approvals, and customer contracts
- Contract dependency
- Allocation of delay, nonperformance and termination is not public.
- Capacity boundary
- Projected campus up to 2 GW and TR2 building design up to 55 MW; neither is measured current operating IT load or proven energized phase capacity.
- Uncertainty
- SEC and utility sources were link-only; company claims are not independent verification of uptime or renewable physicality.
1.2 Grid plus dedicated generation
Meta Richland Parish / Hyperion
Coordinating data-center construction with generation, transmission, substation, and regulatory schedule
Internal source tag US01
- Location
- Louisiana
- Grid / utility
- Entergy Louisiana / MISO
- Status at corpus cutoff
- UNDER_CONSTRUCTION
- Power model
- Bespoke utility service with dedicated facilities and customer protections in a public commission proceeding
- Power evidence
- Entergy grid and approved gas-generation buildout; settlement authorizes a 1,500 MW renewable-procurement mechanism. No current physical delivery of that renewable amount is established.
- Legal dependency
- LPSC Order U-37425, effective 2025-08-29, and public settlement conditions; local permit inventory incomplete.
- Contract dependency
- CIAC covers listed network additions; guarantees/minimum charges and early-termination filing conditions appear in public settlement. No full risk elimination established.
- Capacity boundary
- Compute capacity stated by Meta; not equivalent to verified electric demand
- Uncertainty
- Current Meta page contains internally inconsistent 5 GW and over-2-GW language; compute capacity is not treated as electric load.
NEWCheyenne Fuel Cell / AEP–Google dedicated 702 MW supply projectDedicated generation project case
How does an investor-owned utility affiliate sponsor generation dedicated to a hyperscaler's electricity demand?
Internal source tag US07
- Issued / announced
- 2026-10-14
- Evidence status
- ANNOUNCED · 702 MW planned, 0 MW verified energized
- Location
- Near Cheyenne, Wyoming; exact plant-to-data-centre route is not published in the announcement
- Developer / owner
- Cheyenne Fuel Cell, LLC (approximately 92% AEP; 8% Basalt-advised funds)
- Generation technology
- Bloom Energy natural-gas fuel cells; carbon capture integration planned
- Planned capacity
- 702 MW; proposed USD 4 billion investment
- Construction / operation
- Construction planned for 2026, full operation expected end 2028; NOT verified energized
- Commercial counterpart
- 20-year Google PPA; see Contract US-T502
- Public-law dependency
- Detailed siting permissions, utility interconnection and retail-service structure not established from this announcement
1.3 Grid plus dedicated upgrade
Google The Dalles Data Center
Water transparency, municipal capacity, and equitable allocation of infrastructure benefits
Internal source tag US06
- Location
- Oregon
- Grid / utility
- Northern Wasco County PUD / BPA-linked Northwest grid
- Status at corpus cutoff
- OPERATIONAL; EXPANDING
- Power model
- Municipal/public-utility service embedded in regional grid
- Power evidence
- Northwest grid supply and Google portfolio procurement; site-specific hourly physical match not established
- Legal dependency
- Municipal agreements, Oregon strategic investment program, water rights and public-record processes
- Contract dependency
- Allocation of delay, nonperformance and termination is not public.
- Capacity boundary
- No reliable project electrical or IT MW located
- Uncertainty
- No verified site MW; reported PUE is company data, and some municipal water records remain contested or summarized.
1.4 Hybrid
xAI Colossus
Synchronizing extreme compute deployment with grid upgrades, air permitting, and community legitimacy
Internal source tag US03
- Location
- Tennessee
- Grid / utility
- Memphis Light, Gas and Water / Tennessee Valley Authority
- Status at corpus cutoff
- OPERATIONAL; EXPANDING
- Power model
- Municipal-utility service with customer-funded upgrades, curtailment agreement, and temporary on-site generation
- Power evidence
- MLGW/TVA grid; permit records cover on-site gas generation (15 specified turbines in 2025 construction permit; proposed reduction to 12 in 2026 notice). Historical unpermitted-use allegations remain attributed.
- Legal dependency
- TVA/MLGW service process; Shelby construction permit 01156-01PC and later operating-permit notice; environmental objections and review remain distinct from findings.
- Contract dependency
- No verified minimum-bill/termination formula in accessed utility update
- Capacity boundary
- Documented grid supply across two substations; not total facility maximum
- Uncertainty
- Memphis sites are not merged. Permit issuance, proposed operating-permit conversion, allegations and appeal outcome are separate procedural states. Full turbine inventory and final appeal disposition require verified records.
2. China
2.1 Full grid
Alibaba Zhangbei Miaotan Data Center
Turning regional wind availability into temporally matched compute consumption
Internal source tag CN05
- Location
- Hebei
- Grid / utility
- Zhangjiakou / Zhangbei grid region; contracted utility legal entity not verified.
- Status at corpus cutoff
- OPERATIONAL
- Power model
- Grid-connected hyperscale load using regional renewable market transactions
- Power evidence
- Market-purchased wind under a four-party mechanism; renewable share reported above 50%
- Legal dependency
- Energy-consumption review, project filings, electricity-market arrangements
- Contract dependency
- Allocation of delay, nonperformance and termination is not public.
- Capacity boundary
- No reliable project electrical MW located; 4,000 racks and up to 100,000 servers reported
- Uncertainty
- Some electrical assets belong to the broader Zhangbei base, not solely Miaotan; sustainability outcomes are reported rather than independently measured. Alibaba 2025 workload-shifting and 13,680 GJ heat statements concern a Zhangbei data center without naming Miaotan; retained only as broader-region context.
2.2 Green direct connect
Zhongjin Wulanchabu Zero-Carbon Compute Base
Synchronizing compute load with dedicated generation and storage while preventing reverse export
Internal source tag CN04
- Location
- Inner Mongolia
- Grid / utility
- Inner Mongolia power system
- Status at corpus cutoff
- OPERATIONAL; EXPANDING
- Power model
- Source-grid-load-storage direct connection with load-before-generation sequencing
- Power evidence
- Dedicated wind/solar design, storage and grid interface; direct-linkage and output reports do not establish full hourly matching or complete commissioning.
- Contract dependency
- Conditional rule: if actual post-operation load underperforms declared curve and causes wind/solar curtailment, relevant enterprises and municipality bear investment loss. No actual loss proven.
- Capacity boundary
- Conditional implementation-notice load design; not firm delivered/commissioned power.
- Uncertainty
- Reported operating status is not a commissioning certificate. The loss rule is contingent, and no actual demand collapse or curtailment loss is proven.
NEWDatang Zhongwei Cloud Base 500 MW photovoltaic green direct-supply projectCompute–power coordinated PV generation and direct-supply case
How do physical direct-supply lines for incremental compute load coexist with bilateral green-power trading for existing load?
Internal source tag CN07
- Issued / announced
- 2026-05-02
- Evidence status
- 500 MW PV CONFIRMED OPERATIONAL 2026-05-02 · additional 1,500 MW wind NOT verified commissioned
- Location
- Zhongwei, Ningxia; project associated with the Zhongwei Cloud Base
- Verified installed generation
- 500 MW PV project commissioned 2026-05-02
- Separate planned generation
- 1,500 MW wind described in official May publication as planned for September 2026; no later commissioning evidence verified in this update
- Power arrangement
- Physical dedicated transmission for new/incremental loads; bilateral market transactions for existing loads
- Project-scale caveat
- Broader first-phase plan totals 2 GW (0.5 GW PV + 1.5 GW wind); this figure is NOT verified operational capacity
- Evidence basis
- Datang statement republished by SASAC and NEA-affiliated information source; commissioning was described by project developer
2.3 Grid plus dedicated upgrade
GDS Kunshan Guojin Data Center REIT
Preserving contract continuity and power access while separating operating assets and the incoming-line asset
Internal source tag CN01
- Location
- Jiangsu
- Grid / utility
- Jiangsu grid / Kunshan power bureau
- Status at corpus cutoff
- OPERATIONAL
- Power model
- Grid-served wholesale colocation with electricity excluded from hosting fee
- Power evidence
- Jiangsu/Kunshan grid; customers bear metered electricity through pass-through model
- Legal dependency
- SSE REIT rules, fund/ABS contracts, land title, VATS license, asset-transfer agreements
- Contract dependency
- Renewal agreements lack dedicated renewal-breach liability and future fee/growth terms; demand, collection and access risk remain.
- Capacity boundary
- Designed rack electrical capacity across 4,192 racks; not total facility load
- Uncertainty
- March and June 2026 prospectus updates state no supplementary due diligence or material asset refresh. Most asset facts remain as of March 2025; no later renewal outcome or full-year 2025 operating dataset established. Customer identities and terms are disclosed as of 2025-03-31; Shanghai Telecom's initial term ended 2025-07-31 and later renewal/current status is not established.
Chindata Huailai / Taihang Campus
Customer concentration, ramping nearly 500 MW, and converting renewable availability into delivered clean power
Internal source tag CN02
- Location
- Hebei
- Grid / utility
- Zhangjiakou / Huailai grid region; contracted utility legal entity not verified.
- Status at corpus cutoff
- OPERATIONAL; EXPANDING
- Power model
- Grid-connected wholesale campuses with long-term customer contracts and regional renewable procurement
- Power evidence
- Huailai regional grid (contracted legal entity not verified); 2024 Huailai green procurement share reported above 30%, not hourly physical matching.
- Legal dependency
- Enterprise approvals, grid construction contracts, customer service agreements
- Contract dependency
- Allocation of delay, nonperformance and termination is not public.
- Capacity boundary
- Government/company aggregate for operating plus under-construction Huailai capacity; not current energized IT load
- Uncertainty
- Some figures are corporate or county-level and cannot be allocated precisely to one campus; the 2022 20-F was link-only. FLAGSHIP_EVIDENCE_GAP — CN02 is retained solely for its customer-concentrated private-wholesale/ownership-transition mechanism. Core contract and concentration evidence is company-wide, the nearly 500 MW figure is a Huailai operating-plus-construction aggregate, and no complete site-level permit, commissioning, utility-contract, financing or impact file was recovered. Environmental completeness is 2 because the required multi-track search was performed and logged; it does not imply favorable findings or absence of issues. Exclude CN02 from precise timing, capacity and project-outcome comparisons.
China Telecom Qingyang Intelligent-Compute Center
Synchronizing data halls, phase-specific grid supply and customer utilization. Regional renewable works are contextual, not a verified project supply entitlement.
Internal source tag CN03
- Location
- Gansu
- Grid / utility
- State Grid Gansu
- Status at corpus cutoff
- OPERATIONAL; EXPANDING
- Power model
- Grid-connected state-carrier project in a national compute hub; 110 kV works reported. Renewable aggregation is cluster context; project allocation and delivery contract not established.
- Power evidence
- Public-grid supply; project-specific electricity mix not established. The Qingyang cluster renewable-aggregation program is regional context, not verified supply allocation to China Telecom.
- Legal dependency
- NDRC hub approval, planning permit, EPC procurement
- Contract dependency
- Allocation of delay, nonperformance and termination is not public.
- Capacity boundary
- Renewable aggregation program first-phase/program scale; not data-center IT load
- Uncertainty
- Several current sources were link-only; 1,000 MW refers to an energy program, not compute capacity. FLAGSHIP_EVIDENCE_GAP — CN03 is retained for the state-carrier national-hub and staggered compute/grid/renewable delivery mechanism. Four of five sources are URL-only; 1,000 MW is renewable-program scale, not compute capacity; and the substation, permit, customer-contract, financing and operating-impact files remain incomplete. Environmental completeness is 2 because the required multi-track search was performed and logged; it does not imply favorable findings or absence of issues.
Tencent Qingyuan Qingxin Cloud Data Center
Reconcile building expansion, grid/substation delivery and energy-review authorization; rectification closure remains unresolved in accessed records.
Internal source tag CN06
- Location
- Guangdong
- Grid / utility
- Guangdong Power Grid, Qingyuan Power Supply Bureau; Southern Grid region.
- Status at corpus cutoff
- OPERATIONAL; EXPANDING
- Power model
- Grid-connected phased campus with limited on-site renewable generation
- Power evidence
- Guangdong grid plus 6.6 MW rooftop solar connected in 2021
- Legal dependency
- Energy-review approved scale and utility-support ceiling constrain lawful power access. 2023 rectification ordered; no later closure, withdrawal or final compliance finding verified.
- Contract dependency
- Allocation of delay, nonperformance and termination is not public.
- Capacity boundary
- 2019 plan: 300,000 servers, not MW. 2023 inspection: 7,950 cabinets at 7.2 kW plus 480 at 6 kW, equivalent to 24,048 standard 2.5-kW cabinets; approved 1,728 equivalents. Design/inspection cabinet ratings are not measured IT MW. 6.6 MW PV is generation nameplate.
- Uncertainty
- No rectification acceptance/closure or revised energy-review instrument verified after the 2023 order. Do not infer current illegality or compliance. Do not combine Qingxin and Qingcheng, annual kWh with peak MW, or PV nameplate with compute load.