One bargain.
Two contexts.
The same supply commitment meets different rules on market access, grid service and enforcement. Follow who promises what—and who bears the cost when demand changes.
New evidence · 19 October 2026
Newly added to the research atlas. Source publication dates and evidence status appear in each record.
Follow how contracts allocate risk.
1. United States
1.1 Colocation compute capacity
Digi Power X–Cerebras 40 MW colocation MSA
How does a compute customer become the anchor for energy-infrastructure finance?
Internal source tag US-T004
- Project
- Digi Power X Alabama AI Campus
- Parties
- Digi Power X Inc.; Cerebras Systems Inc.
- Instrument type
- COLOCATION_MASTER_SERVICES_AGREEMENT
- Status at corpus cutoff
- EXECUTED_OR_EFFECTIVE
- Public/private boundary
- Private MSA allocates delivery, acceptance and service-level risk
- Disclosure
- REDACTED_EXECUTED_CONTRACT
- Legal interface
- Delaware-law private contract sits downstream of utility supply
- Critical unknown
- Pricing, escalation and several liability terms are redacted
- Corpus review
- Executed MSA supports 15 MW Phase 1 plus conditional 25 MW Phase 2, 10-year take-or-pay-style capacity charges, Tier III/UPS/diesel requirements, tariff and government-charge pass-through, and SLA credits. Do not infer a customer termination payment from customary remedies or redacted language.
TeraWulf–Fluidstack 378 MW leases with Google credit support
Who is the economically relevant customer when an intermediary signs but a hyperscaler supports credit?
Internal source tag US-T012
- Project
- Akela Data Center Campus
- Parties
- TeraWulf subsidiaries; Fluidstack; Google credit-support provider
- Instrument type
- DATA_CENTER_LEASES_AND_CREDIT_SUPPORT
- Status at corpus cutoff
- EXECUTED_OR_EFFECTIVE
- Public/private boundary
- Private credit support changes financeability without changing utility regulation
- Disclosure
- PROSPECTUS_DISCLOSURE
- Legal interface
- Private structure leverages existing grid/site entitlements
- Critical unknown
- Support amount, expiry, conditions and lease termination waterfall
- Corpus review
- Google credit support is disclosed, but the public prospectus does not establish that the instrument is a parent guaranty or disclose its complete scope. The 378 MW figure aggregates three Fluidstack leases and must not be treated as one phase or one site's currently operational load.
Alliance Cloud Services–neocloud 20 MW MSA
How much schedule risk can a colocation provider push downstream before service begins?
Internal source tag US-T017
- Project
- Hyperscale Data Michigan Campus
- Parties
- Alliance Cloud Services, LLC; redacted neocloud customer
- Instrument type
- COLOCATION_MASTER_SERVICES_AGREEMENT
- Status at corpus cutoff
- EXECUTED_OR_EFFECTIVE
- Public/private boundary
- Private license/service contract relies on utility delivery and diesel commissioning
- Disclosure
- REDACTED_EXECUTED_CONTRACT
- Legal interface
- Utility and permitting delays are contractually externalized
- Critical unknown
- Customer identity, recurring charges and some default economics
- Corpus review
- No public LC requirement was identified; do not convert silence into NO. Contract directly supports cash deposit/NRC, two delivery phases, delay credits and phase termination mechanics, and a temporary diesel-backup carve-out.
1.2 Grid interconnection
TeraWulf–Kentucky Power 500 MW ESA and 1 GW LOA
Is power-delivery security economically equivalent to project equity?
Internal source tag US-T009
- Project
- Muskie Data Campus
- Parties
- TeraWulf subsidiary; Kentucky Power Company
- Instrument type
- ELECTRIC_SERVICE_AND_LOAD_AGREEMENT
- Status at corpus cutoff
- EXECUTED_OR_EFFECTIVE
- Public/private boundary
- Private ESA/LOA governs facilities embedded in regulated utility network
- Disclosure
- FILING_SUMMARY
- Legal interface
- Utility agreements operationalize regulated interconnection investment
- Critical unknown
- Executed agreement text, refund milestones and precise collateral draw rules
- Corpus review
- Detailed Note 3 says ESA capacity ramps to 500 MW, initial term 20 years from the in-service date (no earlier than 2028-10-13), and ESA/LOA support up to 1 GW. Later Operations Overview calls the ESA 1,000 MW. Retain MW_contract=500 only with this conflict note; MW_requested=1,000 is the broader infrastructure/site scope.
1.3 Onsite energy fuel supply
TerraVolt 55,000 MMBtu/day firm natural-gas supply agreement
Can a fuel contract replace grid interconnection as the primary power commitment?
Internal source tag US-T011
- Project
- TerraVolt Southeast Idaho campus
- Parties
- TerraVolt; undisclosed natural-gas marketer
- Instrument type
- NATURAL_GAS_SUPPLY_AGREEMENT
- Status at corpus cutoff
- FUEL_AGREEMENT_ANNOUNCED_EXECUTED; POWER_PLANT_AND_CAMPUS_PLANNED
- Public/private boundary
- Private fuel supply cannot eliminate permitting and pipeline constraints
- Disclosure
- ISSUER_RELEASE_ONLY
- Legal interface
- Public permits remain gating conditions despite private firm supply
- Critical unknown
- Counterparty, term, price, take-or-pay, transport and remedies
- Corpus review
- The SEC-filed release supports execution, firm daily gas quantity, an unnamed top-tier gas marketer, and fuel-management services. The 200-240 MW figure is only the planned initial power-plant range, while all campus construction/permitting statements are forward-looking. Onsite generation is described as primary BTM supply, not backup generation.
1.4 Onsite power equipment
SEI 600+ MW power-equipment rental agreement
Does temporary/onsite generation substitute for delayed grid access?
Internal source tag US-T010
- Project
- Customer C AI data-center power-equipment deployment (site scope undisclosed)
- Parties
- Solaris Energy Infrastructure affiliate; undisclosed customer affiliate of an investment-grade global technology company
- Instrument type
- MASTER_EQUIPMENT_RENTAL_AGREEMENT
- Status at corpus cutoff
- EXECUTED; DEPLOYMENT_PLANNED_2026_TO_2028
- Public/private boundary
- Private equipment contract may bridge public-grid delay but remains permit-dependent
- Disclosure
- FILING_SUMMARY
- Legal interface
- Environmental and local permits remain external conditions
- Critical unknown
- Customer identity, exact site count/locations, fuel responsibility, price, acceptance, uptime, credit support, and termination remedies
- Corpus review
- The cited Q1 10-Q discloses an agreement signed 2026-04-24 for over 600 MW and deployments from late 2026 through 2028. It does not prove 600 MW of delivered AI load, backup-generator status, or take-or-pay. Preserve 'over 600 MW' in text rather than a numeric 600 MW cell.
1.5 Power purchase clean energy
Talen–AWS nuclear PPA and BTM-to-front-of-meter restructuring
When does a private direct supply arrangement become a wholesale transmission issue?
Internal source tag US-T014
- Project
- AWS Susquehanna Data Campus
- Parties
- Talen/Susquehanna Nuclear; Amazon Energy/AWS; PPL Electric; PJM
- Instrument type
- POWER_PURCHASE_AND_INTERCONNECTION_RESTRUCTURING
- Status at corpus cutoff
- EXECUTED_OR_EFFECTIVE
- Public/private boundary
- FERC jurisdiction altered viable delivery topology
- Disclosure
- FILING_AND_REGULATORY_ORDER
- Legal interface
- FERC rejection led parties to a revised retail/front-of-meter architecture
- Critical unknown
- Full PPA price, termination and attribute schedules
- Corpus review
- Commercial amendment facts derive from Talen's A3 filing; the 2024 FERC order is A2 only for the rejected ISA phase. Keep the 2024 rejected 480 MW BTM amendment distinct from the operative 2025 amended PPA and front-of-meter transition. Do not infer REC transfer from nuclear generation alone.
Constellation–Microsoft 20-year nuclear PPA
Can hyperscaler demand finance reactivation of existing zero-carbon generation?
Internal source tag US-T015
- Project
- Crane Clean Energy Center
- Parties
- Constellation Energy; Microsoft
- Instrument type
- POWER_PURCHASE_AGREEMENT
- Status at corpus cutoff
- PPA_EXECUTED; PLANT_RESTART_SUBJECT_TO_NRC_AND_PJM_PROCESSES
- Public/private boundary
- Private PPA depends on nuclear licensing and grid interconnection
- Disclosure
- SEC_FILED_PARTY_RELEASE
- Legal interface
- NRC/PJM outcomes remain external to private offtake
- Critical unknown
- Price, volume profile, attributes and termination
- Corpus review
- Approximately 835 MW is the plant's expected output/nameplate context, not a disclosed contract-demand quantity. The party release supports a 20-year PPA and grid-based matching of Microsoft PJM load, but not take-or-pay, phasing, direct wire, or REC mechanics.
TotalEnergies–Google two 15-year solar PPAs
Does annual clean-energy procurement hedge the operational risk of 24/7 AI load?
Internal source tag US-T016
- Project
- Wichita and Mustang Creek solar projects
- Parties
- TotalEnergies; Google
- Instrument type
- POWER_PURCHASE_AGREEMENTS
- Status at corpus cutoff
- EXECUTED_OR_EFFECTIVE
- Public/private boundary
- Corporate PPAs rely on public grid settlement and renewable attributes
- Disclosure
- SEC_FILED_PARTY_RELEASE
- Legal interface
- Market settlement and renewable-certificate rules define delivery meaning
- Critical unknown
- Price, settlement point, curtailment and certificate schedule
- Corpus review
- The SEC-filed party release supports two signed 15-year PPAs, projects of 805 MWp and 195 MWp, and approximately 28 TWh aggregate contracted output. It does not disclose take-or-pay, direct-wire status, replacement energy, REC title/retirement, or hourly matching.
NEWGoogle–Constellation 20-year nuclear uprate PPA (890 MW new capacity)Power purchase and strategic energy collaboration
Can a long-term hyperscaler PPA underwrite incremental nuclear capacity while keeping generation available to the regional grid?
Internal source tag US-T501
- Issued / announced
- 2026-10-06
- Evidence status
- ANNOUNCED AGREEMENT · uprates planned; first output expected by 2028
- Parties
- Google; Constellation Energy
- New capacity
- 890 MW planned incremental nuclear output at 11 existing nuclear units in PJM
- Term
- 20-year PPA supporting incremental capacity; additional 15-year agreement for 2,700 MW of existing PJM generation
- Distinction
- 2,700 MW represents existing supply commitments, not additional capacity; 890 MW uprate is not yet operating
- Disclosure
- Official corporate announcement; signed PPA text and proprietary pricing not publicly verified
NEWAEP–Google Cheyenne Fuel Cell 20-year PPA (702 MW planned)Dedicated-generation power purchase agreement
How does a dedicated natural-gas fuel-cell power contract allocate project-development and delivery risk across a hyperscaler and an investor-owned utility affiliate?
Internal source tag US-T502
- Issued / announced
- 2026-10-14
- Evidence status
- ANNOUNCED PPA · fuel-cell project planned, not operating; carbon capture aspirational
- Parties
- Cheyenne Fuel Cell, LLC (approximately 92% AEP; approximately 8% Basalt-advised funds); Google
- Capacity / location
- 702 MW fuel cells near Cheyenne, Wyoming; approximate planned investment USD 4 billion
- Commercial term
- 20-year PPA; agreement announced, contract text and risk clauses not publicly available
- Development status
- Construction planned to start in 2026; full operation expected by end of 2028
- Environmental caveat
- Natural-gas fuel-cell generation without combustion; carbon capture is proposed, not operationally demonstrated
- Classification caveat
- Filed with energy purchase arrangements for comparability; gas fuel cells are NOT established as clean or zero-carbon
NEWAmazon–Constellation Calvert Cliffs 20-year nuclear PPA (690 MW total; 190 MW uprate)Nuclear power purchase and related retail supply agreement
How can a long-term corporate offtake commitment support nuclear uprates and relicensing without physically co-locating the data centre?
Internal source tag US-T503
- Issued / announced
- 2026-09-30
- Evidence status
- ANNOUNCED AGREEMENT · additional 190 MW projected for 2030–2032
- Parties
- Amazon; Constellation Energy
- Contract scope
- 20-year agreement for 690 MW INCLUDING 190 MW incremental uprate; related retail supply agreement for Amazon's PJM operations
- Timing
- Additional 190 MW expected online from 2030 to 2032
- Distinction
- Do not add 690 + 190 MW; this is not a new Amazon data-centre campus at Calvert Cliffs
- Disclosure
- Company announcement, not full public executed agreement; individual price and termination terms unverified
1.6 Utility large load service
AEP Ohio large-load service architecture
How does a regulated utility screen speculative AI load without socializing network cost?
Internal source tag US-T001
- Project
- AEP Ohio Data Center Tariff
- Parties
- AEP Ohio; qualifying data-center customers
- Instrument type
- REGULATED_TARIFF_AND_STANDARD_CONTRACTS
- Status at corpus cutoff
- EFFECTIVE
- Public/private boundary
- Commission-approved tariff sets mandatory floor; bilateral LOA/ESA implements project
- Disclosure
- OFFICIAL_UTILITY_SUMMARY; OPERATIVE_ORDER_METADATA_ONLY; CUSTOMER_SPECIFIC_LOA_ESA_NOT_PUBLIC
- Legal interface
- Regulatory tariff incorporates bilateral agreements and may change prospectively
- Critical unknown
- No executed customer-specific LOA or ESA schedule is public; conditional collateral forms must not be coded as universal requirements
- Corpus review
- AEP's BTM control applies only if the customer elects to net BTM output against contract capacity. It requires instantaneous load curtailment sufficient to prevent a capacity exceedance; it is not a general demand-response obligation. Load ramping is not phased utility energization.
Dominion large-load tariff architecture
Can one tariff distinguish system cost by functional layer?
Internal source tag US-T002
- Project
- Dominion Virginia GS-5
- Parties
- Dominion Energy Virginia; GS-5 customers
- Instrument type
- REGULATED_TARIFF
- Status at corpus cutoff
- APPROVED
- Public/private boundary
- State commission determines tariff; project schedule and security are customer-specific
- Disclosure
- FINAL_ORDER; CUSTOMER_SPECIFIC_ESAS_NOT_PUBLIC
- Legal interface
- Commission order controls over earlier testimony or stipulations
- Critical unknown
- Customer-specific ESA and the later compliance tariff sheets are not public in the archived record; no universal cash-deposit, LC, or parent-guarantee requirement should be inferred
- Corpus review
- Final Order pp. 24-26 controls. The 70% collateral reduction is based on established credit; do not import a precise rating threshold from proposal testimony.
Georgia PSC data-center contract review and minimum-bill framework
Does ex ante contract review substitute for standardized tariff detail?
Internal source tag US-T003
- Project
- Georgia Power large-load rule
- Parties
- Georgia Power; large-load data-center applicants
- Instrument type
- REGULATED_RULE
- Status at corpus cutoff
- APPROVED
- Public/private boundary
- Regulator requires visibility into customer contracts before execution
- Disclosure
- REGULATOR_FACT_SHEET
- Legal interface
- Private contract is conditioned by regulator-facing disclosure
- Critical unknown
- Exact operative rule/tariff language and every customer-specific contract remain nonpublic in the cited fact sheet
- Corpus review
- The PSC source says the rule allows minimum bills and longer terms (from 5 to 15 years); it does not prove a 15-year term, take-or-pay formula, or termination payment in any particular contract.
One Blockchain–local utility 65,000 kVA ESA
How does a utility commitment become a prerequisite to AI-site finance?
Internal source tag US-T005
- Project
- CLT01
- Parties
- One Blockchain, LLC; redacted local utility
- Instrument type
- ELECTRIC_SERVICE_AGREEMENT
- Status at corpus cutoff
- EXECUTED_OR_EFFECTIVE
- Public/private boundary
- Executed contract incorporates public rate schedule and future regulatory changes
- Disclosure
- REDACTED_EXECUTED_CONTRACT
- Legal interface
- Rate schedule changes automatically displace inconsistent agreement terms
- Critical unknown
- Utility identity, jurisdiction and some incorporated tariff terms are redacted
- Corpus review
- §1: 65,000 kVA at approximately 34.5 kV. §3: 2026-12-15 target, subject to enumerated relief and prior BPV ESA termination. §4: 15 years from Initial Delivery Date. §5: minimum bill. §7: required deposit with cash, surety, or another industrial customer's guarantee alternatives. §8: $250,000 fee. §9: only future possible PPA provisions. §10: utility may request operation of backup generation.
DTE Electric-Green Chile Ventures 1,383 MW primary supply package (Oracle-guaranteed)
Can utility-owned assets be financed around a single investment-grade AI customer?
Internal source tag US-T006
- Project
- DTE–Oracle data-center load package
- Parties
- DTE Electric Company; Green Chile Ventures LLC; Oracle Corporation as Customer Parent Guarantor
- Instrument type
- PRIMARY_SUPPLY_AGREEMENT
- Status at corpus cutoff
- CONDITIONALLY_APPROVED_BY_MPSC; AG_APPEAL_FILED_AS_OF_AUGUST_2026; LATER_APPELLATE_DISPOSITION_NOT_OBSERVED
- Public/private boundary
- Private PSA is conditioned on commission approval and linked storage agreement
- Disclosure
- REDACTED_EXECUTED_CONTRACT
- Legal interface
- Commission approval and linked agreements are conditions precedent
- Critical unknown
- Public PSA redacts the capacity ramp, energization schedule, Schedule 8 LC amounts, pricing, and substantial default language; the separate storage agreement is not public
- Corpus review
- Contract Date is 2025-10-22. Initial Term runs from Commencement Date to 2045-02-28, with up to two optional 10-year renewals (§§3.1-3.2). Effective Date is when §4 conditions are satisfied and is not the Contract Date. Exact regulatory capacity is 1,383 MW; 1.4 GW is rounded.
DTE Electric-Google 1.0 GW primary supply agreement
How are decarbonization, flexibility and credit bundled into retail service?
Internal source tag US-T007
- Project
- DTE–Google data-center load package
- Parties
- DTE Electric Company; Google LLC (customer)
- Instrument type
- PRIMARY_SUPPLY_AGREEMENT
- Status at corpus cutoff
- EXECUTED_SUBJECT_TO_MPSC_APPROVAL; PROPOSAL_PROCEEDING_ACTIVE_AS_OF_2026-06-11; LATER_DISPOSITION_NOT_OBSERVED
- Public/private boundary
- PSA conditions private obligations on MPSC approval and system-emergency rules
- Disclosure
- REDACTED_EXECUTED_CONTRACT_PLUS_PARTY_RECONSTRUCTION
- Legal interface
- MPSC approval and MISO emergency instructions condition performance
- Critical unknown
- Final MPSC disposition; redacted capacity/energization schedules and credit support; full CCAA, demand-response, and line-extension economics
- Corpus review
- The 2026-03-12 amended and restated PSA supersedes the 2025-12-17 Original PSA. Google LLC is the customer, not merely a guarantor. The PSA proves the companion agreements' existence and contractual interfaces, but not the public presentation's portfolio MW figures as executed PSA obligations.
Evergy 2026 data-center ESA portfolio
Can portfolio diversification substitute for single-customer collateral?
Internal source tag US-T008
- Project
- Evergy large-load portfolio
- Parties
- Evergy utilities; three new and two expanding data-center customers
- Instrument type
- AGGREGATE_ELECTRIC_SERVICE_AGREEMENTS
- Status at corpus cutoff
- EXECUTED_OR_EFFECTIVE
- Public/private boundary
- Individual ESAs remain private under public LLPS frameworks
- Disclosure
- AGGREGATE_FILING_DISCLOSURE
- Legal interface
- Private ESAs take service under commission-approved LLPS tariffs
- Critical unknown
- Customer identities, individual contracted MW, individual terms, minimums, security, and exit rights
- Corpus review
- 10-Q p.59 states only that Evergy signed ESAs for three new and two expanding projects, with aggregate projected peak steady-state load about 2,600 MW; terms reflect applicable LLPS plans; service has commenced or is expected 2026-2028, inclusive of optional transition periods up to five years. It does not restate a 15-year or 80% transaction term.
Xcel/NSP >100 MW large-load tariff
How do regulators define the class of load that must pre-commit?
Internal source tag US-T013
- Project
- NSP Minnesota large-load tariff
- Parties
- Northern States Power Company–Minnesota; qualifying customers
- Instrument type
- REGULATED_TARIFF
- Status at corpus cutoff
- APPROVED
- Public/private boundary
- Commission tariff disciplines private customer commitments
- Disclosure
- 10-Q SUMMARY_OF_ORDER
- Legal interface
- Public tariff supplies mandatory private contracting baseline
- Critical unknown
- Final tariff text, minimum percentage and security formula
- Corpus review
- Issuer 10-Q is A3 and summarizes the regulatory outcome. Do not code a specific security form, amount, minimum percentage, or customer-specific term unless the final commission order/tariff is separately captured.
2. China
2.1 Capital recycling
Southern GDS Data Center REIT initial offering
How are data-center power and customer risks transformed into a listed yield product?
Internal source tag CN-T003
- Project
- Southern GDS Data Center C-REIT
- Parties
- GDS; Southern Asset Management; project companies; public fund investors
- Instrument type
- PUBLIC_INFRASTRUCTURE_REIT
- Status at corpus cutoff
- INITIAL OFFERING COMPLETED; LISTED AND TRADING SINCE 2025-08-08
- Public/private boundary
- Public securities/fund rules convert private service cash flows into regulated infrastructure income
- Disclosure
- FULL_PROSPECTUS_WITH_CONTRACT_SUMMARIES
- Legal interface
- REIT regulation overlays project-company, operations and customer contracts
- Critical unknown
- Full customer contracts, remedies, transaction-specific MW, renewable procurement/GEC terms and any validated capex-overrun undertaking
- Corpus review
- The 2026-03-03 prospectus is an update, not the initial offering. Its face page says the fund was registered on 2025-06-16 and that the update mainly changes the fund manager/format, with no supplemental due diligence or material asset update.
GDS private REIT/ABS capital recycling
Does securitization move risk or only refinance it?
Internal source tag CN-T004
- Project
- CITIC Securities–GDS 2025 Phase 1 Data Centers ABS
- Parties
- GDS; CITIC Securities; institutional investors led by China Life; project companies
- Instrument type
- PRIVATE_REIT_AND_ASSET_BACKED_SECURITIES
- Status at corpus cutoff
- COMPLETED IN Q1 2025; APPROXIMATELY RMB700M REMAINING CONSIDERATION CONTINGENT ON RAMP-UP MILESTONES
- Public/private boundary
- Private/institutional capital vehicle operates under exchange and securities rules
- Disclosure
- ISSUER_FILING_SUMMARY
- Legal interface
- Exchange/ABS rules package private contracts into investable claims
- Critical unknown
- Underlying fund/ABS plan, equity-transfer and operating agreements, waterfall, milestone definitions, customer obligations and asset-specific power terms
- Corpus review
- CN-S006 is a 2025-03-10 definitive-agreement announcement, not completion evidence. Completion during Q1 2025 and the milestone-contingent balance are reported in the Q1-results exchange filing.
VNET–Dajia pre-REIT fund cooperation
How does anticipated securitization influence construction and customer contracting?
Internal source tag CN-T008
- Project
- VNET Taicang Data Centers
- Parties
- VNET; Dajia Investment Holding and partners
- Instrument type
- PRE_REIT_COOPERATION_FRAMEWORK
- Status at corpus cutoff
- COOPERATION FRAMEWORK SIGNED; FUND CLOSING, FUNDING AND ASSET TRANSFER UNKNOWN
- Public/private boundary
- Private fund anticipates later regulated REIT/capital-market exit
- Disclosure
- ANNUAL_REPORT_SUMMARY
- Legal interface
- Capital-market eligibility shapes asset and contract standardization
- Critical unknown
- Fund formation/closing, capital commitments, asset transfer, valuation, waterfall, power allocation and operator obligations
- Corpus review
- Never map the 210 MW target-asset descriptor into MW_contract or MW_requested.
2.2 Colocation compute capacity
VNET 100 MW customer cooperation framework
How should researchers distinguish a headline framework from committed capacity?
Internal source tag CN-T009
- Project
- VNET Ulanqab AI data center
- Parties
- VNET; undisclosed customer
- Instrument type
- CUSTOMER_COOPERATION_FRAMEWORK
- Status at corpus cutoff
- 100 MW FRAMEWORK REPORTED SIGNED IN Q4 2024; 28 MW Q4-2025 DELIVERY PLAN UNVERIFIED
- Public/private boundary
- Private customer framework operates within regional compute and energy policy
- Disclosure
- SEC_FILED_PRESS_RELEASE
- Legal interface
- Regional policy supports location but does not prove private obligation
- Critical unknown
- Binding status, customer identity, price, term, SLA, credit, order conversion and actual Q4-2025 delivery
- Corpus review
- The release says ‘signed a 100MW framework agreement … with 28MW to be delivered in Q4 2025.’ The grammar makes 28 MW a delivery plan, not a disclosed executed tranche.
2.3 Market green power
GDS–China Yangtze Power 2021 hydropower direct-power procurement
How does an operator aggregate renewable procurement across a multi-tenant portfolio?
Internal source tag CN-T005
- Project
- GDS Shanghai data centers 2, 3 and 4
- Parties
- GDS; China Yangtze Power
- Instrument type
- GREEN_POWER_DIRECT_PURCHASE_DISCLOSURE
- Status at corpus cutoff
- EXECUTED_OR_EFFECTIVE
- Public/private boundary
- Private procurement is settled through regional markets and grids
- Disclosure
- PARTY_ESG_REPORT_DISCLOSURE_ONLY
- Legal interface
- Provincial market rules shape private multi-year procurement
- Critical unknown
- Quantity, duration, price, DPP settlement path, GEC ownership, site allocation beyond the three Shanghai sites and remedies
- Corpus review
- Delete every ‘multi-year Yangtze’ assertion. Multi-year modifies the separate CGN New Energy GEC arrangement, not the China Yangtze Power hydropower DPP.
VNET–CGN Solar 2023 green-power purchase agreement with five-year supply-guarantee clause
Can a portfolio-scale green contract create credible environmental claims without hourly data?
Internal source tag CN-T006
- Project
- VNET renewable procurement program
- Parties
- VNET; CGN Solar (Shenzhen)
- Instrument type
- GREEN_POWER_PURCHASE_AGREEMENT
- Status at corpus cutoff
- EXECUTED_OR_EFFECTIVE
- Public/private boundary
- Private contract operates inside state-organized green-power market
- Disclosure
- ANNUAL_REPORT_DISCLOSURE
- Legal interface
- Green-power rules bundle energy and attribute settlement
- Critical unknown
- Whether 500 million kWh is a firm minimum, forecast or cap; price, monthly profile, generation mix, GEC ownership, covered load and remedies
- Corpus review
- Do not infer solar generation merely from the supplier’s corporate name, or GEC/hourly matching from the phrase ‘green power’. CN-S016 postdates this contract and is current regulatory context, not proof of the 2022/2023 terms.
SenseTime interprovincial green-power procurement
What evidence is sufficient to authenticate a green-power claim by a compute operator?
Internal source tag CN-T011
- Project
- SenseTime compute center
- Parties
- SenseTime compute center; Yangtze Delta interprovincial mutual-aid platform; market counterparties not disclosed
- Instrument type
- GREEN_POWER_MARKET_TRANSACTION
- Status at corpus cutoff
- FIRST BATCH GREEN-POWER PROCUREMENT REPORTED COMPLETED IN Q4 2025; UNDERLYING TRADE CONFIRMATION NOT PUBLIC
- Public/private boundary
- Government-organized regional platform enables private consumption transaction
- Disclosure
- OFFICIAL_GOVERNMENT_NEWS
- Legal interface
- Market platform rules substitute for publicly disclosed bespoke contract text
- Critical unknown
- SenseTime volume, price, generator/seller, supply province, delivery interval, settlement, GEC and remedies
- Corpus review
- 5.28×10^8 kWh is 2025 aggregate peak-solar-period export from Anhui through the platform to Shanghai and other areas, not total platform volume and not SenseTime volume. The report says future hourly trading will be explored; do not back-cast that to the Q4-2025 purchase.
2.4 Onsite energy and compute infrastructure
China Mobile–SPIC Qaidam microgrid and EPC package
Can procurement modularity substitute for a single integrated project agreement?
Internal source tag CN-T010
- Project
- China Qaidam Green Microgrid Compute Center
- Parties
- China Mobile Qinghai; SPIC Yellow River Hydropower; China Mobile Design Institute; equipment/EPC contractors
- Instrument type
- PROJECT_CONTRACT_STACK
- Status at corpus cutoff
- PROJECT LAUNCHED; COMPUTE EPC RESULT DISCLOSED; DIESEL PROCUREMENT TENDERED; FULL ENERGY BUILD/COMMISSIONING UNKNOWN
- Public/private boundary
- SOE investment, policy objectives and competitively awarded contracts coexist
- Disclosure
- OFFICIAL_AWARD_AND_PROJECT_DISCLOSURE
- Legal interface
- Public procurement makes some price, scope and award data visible while operating agreements remain opaque
- Critical unknown
- Full signed compute-EPC contract, diesel award, PV/storage procurement and completion, O&M/grid/energy-settlement agreements, acceptance tests and integrated performance guarantees
- Corpus review
- Official tender/award/result notices are A3 transaction disclosures, not A1 executed instruments or A2 regulatory rules. CN-S017 is generic pilot policy and does not prove this project was selected.
2.5 Regulatory direct connection
NDRC/NEA 2025 single-user green direct-connection architecture
How does the state pre-structure a private direct-power transaction?
Internal source tag CN-T001
- Project
- Single-user green electricity direct connection
- Parties
- Project responsible entity; renewable generator; single load user; grid enterprise
- Instrument type
- REGULATORY_ARCHITECTURE
- Status at corpus cutoff
- EFFECTIVE_RULE
- Public/private boundary
- Administrative eligibility and dispatch rules define the menu for private agreements
- Disclosure
- FULL_REGULATORY_TEXT
- Legal interface
- Regulation mandates contract categories and operating ratios but leaves project terms to implementation
- Critical unknown
- Project-specific pricing, security and default remedies
- Corpus review
- Keep regulatory architecture separate from observed transactions. Do not convert required agreement categories, system charges, export controls, or fault responsibility into transaction-specific bankability clauses.
NDRC/NEA 2026 multi-user green direct-connection architecture
Can one project entity aggregate heterogeneous loads without obscuring internal risk?
Internal source tag CN-T002
- Project
- Multi-user green electricity direct connection
- Parties
- Project responsible entity/JV; multiple loads; generators; grid enterprise
- Instrument type
- REGULATORY_ARCHITECTURE
- Status at corpus cutoff
- EFFECTIVE_RULE
- Public/private boundary
- State defines project entity, grid interface and charge obligations; internal parties contract around them
- Disclosure
- FULL_REGULATORY_TEXT
- Legal interface
- National rule makes private internal governance legally indispensable
- Critical unknown
- Transaction-specific governance, security, default and revenue sharing
2.6 State market partnership
VNET–Shandong Hi-Speed renewable-and-compute strategic framework
When does strategic cooperation become an enforceable infrastructure transaction?
Internal source tag CN-T007
- Project
- VNET–Shandong Hi-Speed cooperation
- Parties
- VNET; Shandong Hi-Speed Group
- Instrument type
- STRATEGIC_COOPERATION_AGREEMENT
- Status at corpus cutoff
- STRATEGIC AGREEMENT SIGNED; PROJECT-SPECIFIC IMPLEMENTATION UNKNOWN
- Public/private boundary
- SOE partnership blends commercial and policy roles
- Disclosure
- ANNUAL_REPORT_SUMMARY
- Legal interface
- SOE participation does not by itself establish legal obligation
- Critical unknown
- Whether the strategic agreement is binding beyond cooperation covenants and whether any definitive project agreement, investment or energization followed
- Corpus review
- Do not relabel the disclosed ‘strategic cooperation agreement’ as necessarily non-binding. Its project-specific binding effect and implementation are UNKNOWN. Keep the separate US$299m strategic investment distinct from the energy/compute cooperation agreement.