Ask for the denominator

What do MW, TWh, IT load and national shares actually measure?

Capacity and energy

MW measures power or capacity; TWh measures energy over time. The two cannot be added together, and capacity alone does not establish actual annual consumption.

Illustration: 100 MW × 8,760 hours × 80% utilization = 700,800 MWh, or approximately 0.701 TWh. Both 100 MW and 80% are teaching assumptions, not measurements from a project.

Boundaries and periods

IT load and whole-facility electricity use can have different boundaries. Before applying PUE, establish which components are already included so that cooling and other overheads are not counted twice. Record planned capacity, operational capacity and actual load separately.

The IEA’s 2025 report estimates that data centers used about 415 TWh globally in 2024, with the US and China accounting for roughly 45% and 25%. These shares cover all data center electricity use; they do not measure AI alone or shares of facility counts.

Projections and observations

The same report’s figure of approximately 945 TWh for 2030 is a projection. The Tracker page displays the reference year, unit and projection status together rather than combining unlike figures in an unannotated trend.

Sources & documents

Follow the evidence

Follow the forces
behind AI.

A considered note on the infrastructure that makes intelligence possible. A research summary every other Wednesday, after editorial review.

One argument. Three developments worth reading. New research, original documents and corrections—with the evidence attached.

RSS / Email ↗Leave your email to receive the reviewed summary. Prefer a feed reader? The RSS feed is available on the subscription page.

A conversation in the margins.

0 / 500 characters

Comments are visible to readers of this site. Please keep your message within 500 characters.